Tram Network Upgrade - West Preston substation

10 March, 2017

Public Transport Victoria (PTV) and Yarra Trams are building a new tram power substation on Regent Street in J.S. Grey Reserve, West Preston.

During the past couple of months underground cabling and electrical works have taken place in and around the substation building.

What is planned?

Underground cabling works will be completed on Gilbert Road between the kerb and adjacent tram track. This work will involve reinstatement of asphalt on the carriageway and consists of two main activities:

  • Removal of temporary reinstatement with a small excavator and tip truck
  • Permanent asphalt reinstatement by hand and the use of vibrating compactor

Timing

  • These works are due to occur from Thursday 16 March to Friday 17 March, 2017 between 10:00pm and 5:00am.
  • Further testing and commissioning will be completed by the end of February and will be carried out each weekday between 7:00am-5:30pm, however some occasional work may need to be undertaken on Saturdays between 8:00am-2:00pm.

Architectural treatment

  • The architectural treatment works have commenced and expected to be completed in March 2017.

  • Remediation of the area and landscaping will be carried out in conjunction with these works. The rose garden will now be relocated to the existing garden beds on the corner of Gilbert Road and Regent Street due to availability of space and to allow for optimal sunlight exposure.

J.S Grey Reserve

We have been working with the City of Darebin to investigate an additional contribution to the reserve as part of this project. The following items have been proposed by the City of Darebin. 

  • Raising of the fencing directly behind the basketball hoop to 2.5m
  • Removal and replacement of 3 x park seats
  • Removal and replacement of 1 x picnic setting
  • Installation of 10 x trees
  • Granitic gravel enclosing the existing BBQ setting and new picnic setting
  • Public art to the existing toilet block

Minimising impacts on the local community

  • During this time residents and traders can expect to hear some construction-related noise. Our workers will be mindful of keeping noise to a minimum and respecting the needs of the local community.

Providing a tram network for the future

  • Upgrading tram power is an important part of modernising Melbourne's tram network. This substation at West Preston will provide power to nearby Route 11. Upgrades to substations will deliver a more reliable power supply to support high capacity trams as they are introduced across the network.

Keeping the local community informed

  • PTV and Yarra Trams are committed to keeping the local community informed of construction activity and progress. We thank you for your patience and understanding during this important upgrade work.
  • If you would like to know more about this upgrade, please call 1800 800 007 or email ptvprojects@ptv.vic.gov.au

Tram Network Upgrade - West Preston substation update notification letter (February 2017) (PDF, 235KB)

Tram Network Upgrade - West Preston substation update notification letter (March 2017) (PDF, 173KB)

Tram Network Upgrade - West Preston substation - project newsletter (PDF, 382MB)

Android App
iPhone App
Tramtracker Website App
OR
Journey Planner logo
at  :